Installation & commissioning of control system for new EPF plant at Sinawin oil field NC100.
System Vendor: Siemens
Contractor: Black Gold TS / SGS
End User: Arabian Gulf Oil Company AGOCO
Project Location: North West Libya
Project Status : Completed
Installation & commissioning of custody transfer automatic tank gauging system for 9 floating roof crude oil tanks at Es-sider Terminal.
System Vendor: Emerson
Contractor: Black Gold TS
End User: Waha Oil Company
Project Location: Es-Sider Terminal, Libya
Project Status : On-going
Configuration & Start up of Amal Power Plant ABB 800XA System
System Vendor: ABB Automation
Contractor : Black Gold TS.
End User: Harouge Oil Operation.
Project Location: Amal Oil Field, South West of Libya
Project Status : Completed
Engineering, installation and commissioning of automatic spot ventilation utilizing extracting arms, VSD, static pressure measurement. Extractor speed varies automatically as per room static pressure change.
System Vendor: Fumex
Contractor: Dietsmann Libya
End User: Mellitah Oil & Gas B.V.
Project Location: Mellitah Gas Complex, north west cost, Libya
Project Status : Completed
Installation and configuration of motherboard for Metron Fire Pump FD4e
System Vendor: Hubbell Industrial Controls Inc
End User: Mellitah Oil & Gas B.V.
Project Location: Sharara power station, south west Libya
Project Status : Completed
Installation and Commissioning of CO2 fire extinguishing control panel at El-Feel oil field.
System Vendor: Kentec Electronics ltd
End User: Mellitah Oil & Gas B.V.
Project Location: El-feel oil field, south west Libya
Project Status : Completed